Renewable Energy
Masserano
Masserano | Italy
In Masserano (Biella), Techbau is building a ground-mounted photovoltaic system with a total installed capacity of 15.82 MWp. The system is expected to generate 18.98 GWh of renewable electricity annually, avoiding approximately 7,287 tonnes of CO₂ emissions each year.
The project forms part of the redevelopment of a brownfield site that had been disused for over 25 years. The first phase involved the removal and disposal of asbestos from the roofs, the cleaning of industrial buildings and the remediation of diesel fuel storage tanks. Following the completion of the remediation works, construction of the ground-mounted photovoltaic system has begun, with the aim of bringing new value to the site through renewable energy generation.
MWp
Installed capacity
GWh
Annual energy production
t/year
CO₂ emissions avoided

Aim of the work:
Engineering, Procurement and Construction
Start:
09 / 2025