The project involved the installation of a photovoltaic system on the roof of the logistics complex in San Pietro Mosezzo. With an installed capacity of 9,000 kWp, the system can generate approximately 9.63 GWh of renewable energy per year, avoiding around 3,697 tonnes of CO₂ emissions annually.
The installation contributes to the building’s overall energy performance. The complex was developed in line with ESG principles and the most advanced international standards for environmental sustainability and energy efficiency, achieving LEED Platinum certification, the highest level of recognition under the LEED rating system.
kWp
Installed capacity
GWh
Annual energy production
t/year
CO₂ emissions avoided

Aim of the work:
Engineering, Procurement and Construction
Start:
07 / 2024
End:
09 / 2025