Renewable Energy
Castrezzato
CBRE GLOBAL INVESTORS SGR p.A.
Castrezzato | Italy
The project involved the installation of a photovoltaic system on the roof of the logistics complex in Castrezzato. With an installed capacity of 3,994 kWp, the system can generate approximately 4.27 GWh of renewable energy per year, avoiding around 1,640 tonnes of CO₂ emissions annually.
The installation contributes to improving the building’s overall energy performance. The facility has achieved LEED Platinum certification, the highest level of recognition under the LEED rating system.
3.994
kWp
Installed capacity
4.27
GWh
Annual energy production
1.640
t/year
CO₂ emissions avoided

Aim of the work:
Engineering, Procurement and Construction
Customer:
CBRE Global Investors SGR p.A.
Start:
10 / 2019
End:
08 / 2020
The building is LEED
certified Platinum.